Adaptation of the Last Planner System methodology for the planning and control of industrial engineering projects: a case study
DOI:
https://doi.org/10.47456/bjpe.v11i4.50049Keywords:
last planner system, project planning, industrial projectsAbstract
Context. The Last Planner System (LPS), originally developed for construction, has proved effective in reducing waste and increasing efficiency in project planning and control. This study examined the adaptation of LPS to industrial engineering projects. Objective. To assess LPS’s contribution to efficiency, productivity, and resource management in an engineering context. Method. Case study with two-time windows: February–April 2024 and April–July 2024. LPS routines were implemented, including look ahead meetings, and indicators such as Percentage of Package Completed (PPC) and document advancement across two baselines were monitored. Results. PPC fell within ranges considered acceptable for construction, indicating good performance of the adaptation during the engineering phase. Look ahead meetings brought forward 6 documents in baseline 1 and 36 in baseline 2, helping to reduce schedule deviations. Conclusion. Adapting LPS to the industrial engineering context proved promising. Ongoing adjustments and close monitoring are reinforced as essential to maximise the performance of future projects.
Downloads
References
Agra, A. L. F. (2021). Aplicação da metodologia de construção lean para gestão de suprimentos em uma usina fotovoltaica de grande porte [Trabalho de conclusão de curso, Universidade Federal Rural do Semi-Árido].
Alves, A. C. & Barros Neto, J. P. (2025). Obstáculos para implementação do planejamento de médio prazo: uma revisão sistemática de literatura. Simpósio Brasileiro de Gestão e Economia da Construção, 14(19). Recuperado de https://eventos.antac.org.br/index.php/sibragec/article/view/6670
Ballard, G. (2020). Extending the Last Planner System® to the entire project. Lean Construction Journal, 42-77.
Ballard, G. & Tommelein, I. (2016). Current process benchmark for the Last Planner System. Lean Construction Journal, 89.
Ballard, H. G. (2000). The Last Planner System of Production Control [Doctoral dissertation, University of Birmingham].
Daniel, E. I., Pasquire, C., & Dickens, G. (2019). Development of approach to support construction stakeholders in implementation of the Last Planner System.
Emblemsvåg, J. (2024). Lean project planning - Bridging last planner system and earned value management. Heliyon, 10(18), e37810.
Hamzeh, F., Ballard, G., & Tommelein, I. D. (2012). Rethinking look ahead planning to optimize construction workflow. Lean Construction Journal, 15-34.
Heigermoser, D., et al. (2019). BIM-based Last Planner System tool for improving construction project management. Automation in Construction, 104, 246-254.
Hoyos, M. F. & Botero, L. F. (2018). Evolución e impacto mundial del Last Planner System: Una revisión de la literatura. Ingeniería y Desarrollo, 36(1), 187-214.
Koskela, L. (1999). Management of production in construction: A theoretical view. In Proceedings of the Annual Conference on Lean Construction.
Lean Construction Institute. (2023). Last Planner System standard work. Recuperado de https://leanconstruction.org/wp-content/uploads/2023/10/2023_LCI_LeanConstructionPlannerStandard-Work.pdf
Matias, R. G. & Santos, A. P. L. (2024). Aplicação do Last Planner System: Uma Revisão Sistemática de Literatura. In: Congresso Técnico-Científico da Engenharia e da Agronomia, 2024, [S.l: s.n.].
Polito, G. (2013). Gerenciamento de projetos na construção civil predial: Uma proposta de modelo de gestão integrada. SENAI.
Reck, R. H., Bataglin, F. S., Formoso, C. T., Barth, K. B., Diepenbruck, T., & Isatto, E. L. (2019). Diretrizes para a definição de lotes de montagem de sistemas pré-fabricados de concreto do tipo engineer-to-order. Ambiente Construído, 20(1), 105-127.
Richert, T. (2022). What is the Last Planner System. Lean Construction Blog. Recuperado de https://leanconstructionblog.com/What-is-the-Last-Planner-System-101.html
Silva, T. F. L., & Melhado, S. B. (2014). Diretrizes para a gestão de projetos industriais. Gestão & Tecnologia de Projetos, 9(2), 37-52. https://doi.org/10.11606/gtp.v9i2.81127
Tommelein, I. D. & Ballard, G. (1997). Look ahead planning: Screening and pulling. In Seminário Internacional A Construção sem Perdas (2). Anais, São Paulo.
Tommelein, I., Ballard, G., Howell, G., & Hamzeh, F. (2007). Last Planner System workbook. Recuperado de https://lean-construction-gcs.storage.googleapis.com/wp-content/uploads/2022/08/08161441/Last-Planner-System-Workbook.pdf
Published
Issue
Section
License
Copyright (c) 2025 Trajano, L. T. M., César, C. G., & Nunes, F. A. de S. F.

This work is licensed under a Creative Commons Attribution 4.0 International License.

All works published in the Brazilian Journal of Production Engineering (BJPE) are licensed under Creative Commons Attribution 4.0 International (CC BY 4.0).
This means that:
Anyone can copy, distribute, display, adapt, remix, and even commercially use the content published in the journal;
Provided that due credit is given to the authors and to BJPE as the original source;
No additional permission is required for reuse, as long as the license terms are respected.
This policy complies with the principles of open access, promoting the broad dissemination of scientific knowledge.


2.png)