Schedule management and meeting the demands of an architecture and urban planning office located in the state of Rio de Janeiro - BR
DOI:
https://doi.org/10.47456/bjpe.v10i3.44611Keywords:
Strategies; Real state market; Administration; Crisis., Construction management, BIM programsAbstract
This work involves managing the schedules of an architecture and urban planning office located in the State of Rio de Janeiro, Brazil. The routine, demand and management of the entire office were studied. The objective was to develop and implement an efficient methodology for distributing teams and tasks within the schedule, aiming to optimize the workflow, reduce waste and increase transparency and organizational efficiency. For the methodology, a qualitative approach was used and the technical procedure was the case study. The results were better structuring of management models in the office, combined with methods, software, graphics and programs that enable a clear and didactic reading of management, making it transparent and readable by the entire team.
Downloads
References
Alaghbari, W, Razali A, Kadir, M., Salim, A., & Ernawati. (2007). The significant factors causing delay of building construction projects in Malaysia. Engineering, Construction and Architectural Management. DOI: https://doi.org/10.1108/09699980710731308
Ambler S. W. & Lines, M. (2012). Disciplined agile delivery: A practitioner's guide to agile software delivery in the enterprise. IBM press.
Barreto, F., Conforto, E. C., Amaral, D. C., & Rebentisch, E. (2015). Modelos Híbridos–Unindo complexidade, agilidade e Inovação. Revista Mundo PM, ano, 11, 10.
Barros, J. M. & Silva, S. V. (2022). Gestão de projetos no ramo da arquitetura e construção: revisão sistemática dos métodos, artefatos e seus benefícios. Gestão & Tecnologia de Projetos, 17(2), 127-147. DOI: https://doi.org/10.11606/gtp.v17i2.188695
Batra, D., Xia, W., VanderMeer, D., & Dutta, K. (2010). Balancing agile and structured development approaches to successfully manage large distributed software projects: A case study from the cruise line industry. Communications of the Association for Information Systems, 27(1), 21. DOI: https://doi.org/10.17705/1CAIS.02721
Bianchi, M. J. (2017). Ferramenta para configuração de modelos híbridos de gerenciamento de projetos. Tese de Doutorado. Universidade de São Paulo.
Branski, R. M., Franco, R. A. C., & Lima Junior, O. F. (2010). Metodologia de estudo de casos aplicada à logística. XXIV ANPET Congresso de Pesquisa e Ensino em Transporte (pp. 2023-10).
Campos, V. R. & Azevedo, M. F. (2016). Análise da distribuição de equipes de trabalho na construção civil: estudo de caso. Exacta, 14(3), 339-351. DOI: https://doi.org/10.5585/exactaep.v14n3.6292
Collabo. (2024). O uso do Bim e a possibilidade de reduzir custos e cumprir prazos. Publicado em 06 de setembro de 2017. Recuperado de https://blog.collabo.com.br/o-uso-do-bim-e-possibilidade-de-reduzir-custos-e-cumprir-prazos/
Cristóvão da Cruz, W. (2023). Gestão de pessoas: um estudo acerca do recrutamento e seleção pessoal. Revista OWL (OWL Journal) – Revista interdisciplinar de ensino e educação, 1(1), 14-29.
de Góes, M. B., Rioga, C. L., de Assis Campos, I. L., de Freitas, L. D., Barbosa, S. J., & de Souza, F. T. (2020). Benefícios da implementação do método BIM no planejamento e Gerenciamento de obras. Revista Latino-Americana de Inovação e Engenharia de Produção, 8(14), 107-126. DOI: https://doi.org/10.5380/relainep.v8i14.77617
De Melo A., P. (2008). Gerenciamento da comunicação em projetos: estudo de caso em uma empresa do setor metalúrgico. Tese de Doutorado. Universidade Federal de Juiz de Fora.
Fachin, O. (2001). Fundamentos de metodologias. Saraiva Educação AS.
Gabriel, M.L.D. (2014). Métodos Quantitativos em Ciências Sociais: Sugestões para Elaboração do Relatório de Pesquisa. Desenvolvimento em questão 12(28), 348–369 DOI: https://doi.org/10.21527/2237-6453.2014.28.348-369
Gerhardt, T. E., Souza, A. C. In: Gerhardt, T. E. & Silveira, D. T. (2009). Métodos de Pesquisa. 1ed. Série Educação a Distância. Universidade Aberta do Brasil – UAB/UFRGS. Curso de Graduação Tecnológica – Planejamento e Gestão para o Desenvolvimento Rural da SEAD/UFRGS. Editora da UFRGS, Porto Alegre, RS, Brasil.
Gil, A. C. (2002). Como classificar as pesquisas. Como elaborar projetos de pesquisa, 4(1), 44-45.
Glaser, B. G. & Strauss, A. L. (1967). The Discovery of Grounded Theory: Strategies for Qualitative Research. New York; Aldine de Gruyter. DOI: https://doi.org/10.1097/00006199-196807000-00014
Justi, A. R. (2008). Implantação da plataforma Revit nos escritórios brasileiros. Gestão & Tecnologia de Projetos, 3(1), 140-152. DOI: https://doi.org/10.4237/gtp.v3i1.56
Kerzner, H. (2001). Project Management – A Systems Approach to Planning, Scheduling, and Controlling. Nova York: John Wiley & Sons.
Lopes, S. (2015). Métodos ágeis para arquitetos e profissionais criativos. Brasport. Rio de Janeiro.
Merriam, S. B. & Tisdell, E. J. (2015). Qualitative research: A guide to design and implementation. John Wiley & Sons.
Owolabi, J. D., Amusan, L. M., Oloke, C. O., Olusanya, O., Tunji-Olayeni, P., & Owolabi, D., P. (2014). Causes and effect of delay on project construction delivery time. International journal of education and research, 2(4), 197-208.
Patah, L. A. & Carvalho, M. M. de. (2002). Estruturas de gerenciamento de projetos e competências em equipes de projetos. Anais do Encontro Nacional de Engenharia de Produção, Curitiba, PR, Brasil, p. 23-25.
Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBok). Maryland: Project Management Institute Inc.
Raupp, F. M. & Beuren, I. M. (2006). Metodologia da pesquisa aplicável às ciências. Como elaborar trabalhos monográficos em contabilidade: teoria e prática. São Paulo: Atlas, 76-97.
Salgado, M. S., Magalhães, C. R., dos Santos, E. R., & Canuto, C. L. (2020). A Gestão de projetos e as tecnologias digitais: estratégia BIM-BR e tendências pós-pandemia. Encontro Nacional de Tecnologia do Ambiente Construído, 18(1), 1-8. DOI: https://doi.org/10.46421/entac.v18i.946
Silva, M. V. B. (2015). Gestão do tempo na construção civil e sua relação com as demais áreas da gestão de projetos. Revista On-Line IPOG, 1(10), 1-14.
Silva, L. B. P. & Kovaleski, J. L. (2021). Identificação dos Principais Fatores Causadores de Risco de Atraso em Projetos de Construção Civil: uma Revisão Sistemática da Literatura. Congresso Brasileiro de Engenharia de Produção.
Zanella, L. C. H. (2011). Metodologia de Pesquisa. 2ed. Departamento de Ciências da Administração/Universidade Federal de Santa Catarina [UFSC], Florianópolis, SC, Brasil.
Downloads
Published
Issue
Section
License
Copyright (c) 2024 Brazilian Journal of Production Engineering

This work is licensed under a Creative Commons Attribution 4.0 International License.

All works published in the Brazilian Journal of Production Engineering (BJPE) are licensed under Creative Commons Attribution 4.0 International (CC BY 4.0).
This means that:
Anyone can copy, distribute, display, adapt, remix, and even commercially use the content published in the journal;
Provided that due credit is given to the authors and to BJPE as the original source;
No additional permission is required for reuse, as long as the license terms are respected.
This policy complies with the principles of open access, promoting the broad dissemination of scientific knowledge.


2.png)